Eskom says it will implement Stage 1 and 4 load shedding alternatively until further notice.

The power utility is currently implementing Stage 1 and 3 rolling blackouts.

LOAD SHEDDING FOR THE WEEK

In a statement, Eskom said Stage 1 would be implemented from 05:00 – 16:00 thereafter, Stage 4 would be implemented until 05:00 on Tuesday, 8 August. This will also be repeated on Wednesday.

ALSO READ: Eskom exemption on SO2 emissions to lower load shedding by two stages

Load shedding schedules can be found via the following links:

ALSO READ: Tshwane: Here’s the updated load shedding schedule for Sunday

LATEST ON BREAKDOWNS

Eskom said a generating unit each at Kendal and Tutuka power stations is yet to return to service after delays but two units each at Kriel and a unit each at Camden and Duvha are back online.

As things stand, 15 050MW of capacity is unavailable due to breakdowns and a further 4 434MW is offline due to planned maintenance.

ALSO READ: Ramokgopa will head to China to secure solar panel supply

CLICK HERE TO READ MORE ARTICLES BY NOKWANDA NCWANE

Read original article here

Denial of responsibility! Yours Bulletin is an automatic aggregator of the all world’s media. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials, please contact us by email – admin@yoursbulletin.com. The content will be deleted within 24 hours.

Leave a Comment